Barisal Coal-fired Power Plant Project,Bangladesh
Project Profile
Name: Project of Barisal Coal-fired Power Station in Bangladesh
Location: Barisal Bangladesh
Method: HVDM
Construction duration
From: 2019.02
To: 2020.02
High Vacuum Densification Method(HVDM) was introduced to Bangladesh Barisal Coal-fired Power Station. The HVDM treatment covers the main factory area, living area and the middle channel area,of which the main area and living area are about 508,630 m2, and the middle channel area is about 129,340 m2.The total ground treatment area is about 637,970 m2.